2024/2025 Club Redevelopment Project
The Bribie RSL is thrilled to announce that our eagerly awaited renovations are already underway! The renovations will enhance the Sports Bar, Reception, Bottleshop, Gaming Room, and External Façade, bringing new and exciting upgrades for our members and visitors to enjoy.
These improvements are part of our ongoing commitment to provide the best facilities and experiences for our valued Members. We anticipate that builders, Rubicon Design and Construct, will be onsite from the first week in August setting up site offices and beginning initial outdoor works. Stage 1 (Sports Bar, Reception, Bottleshop & Exterior Façade) will be open in July 2025, closely followed by Stage 2 (gaming room & memorabilia) in October 2025. As with our previous projects, we have planned carefully to ensure minimal disruption to your Club experience. We will continue to operate as close to normal as possible across all departments and are committed to ensuring our service and standards meet your expectations. Regular renovation e-newsletters will be sent to keep our Members up-to-date with progress, along with information on our website and social media pages.
We have included a design of the staged planning, as well as some concept inspiration images. Click here to view the concept inspiration photos.
Your feedback is important to us! If you have any questions or concerns, please feel free to contact us at enquiries@bribiersl.com.au.
Thank you for being part of our incredible community. We can’t wait to unveil our stunning new look and elevate your club experience to new heights!
Kind Regards,
Janelle Barraud
Bribie RSL General Manager
Week 16 Construction Update
Outdoor work continues, plus some indoor action! Here’s this week’s update 18/11/24 to 24/11/24. Here’s a breakdown of the current works:
EXTERNAL HYDRAULICS –
- Aiming to complete the hydraulics inground services to the extension.
SPORTS BAR DEMOLITION –
- Demolition of the Sports Bar & Reception area is on track to be completed this week.
GROUND SLAB –
- Commencement of pouring the ground slab is scheduled for this week subject to good conditions – unfortunately rain is forecast for much of this week.
TERMITE MANAGEMENT:
- Installation of termite management measures to slab & penetrations – subject to progress of concreting.
CHEMSET ANCHOR FIXINGS:
- The first anchor fixings into the concrete footings were installed last week in preparation for steel columns for the Communications room. The columns will be installed once the ground slab has been poured
We continue to do everything possible to minimise noise and inconvenience for you our neighbours. Your understanding and patience are greatly appreciated as we work to improve our facilities!